The Manukau Harbour Crossing Project is an Alliance Delivery model comprising the NZ Transport Agency, Fletcher Construction, Beca Infrastructure and Higgins Contractors

Manukau Harbour Crossing (MHX)

MHX

More [4]  <  >

Start Date

February 2008

Completion Date

2010

 
Higgins Role

Alliance Partner with NZTA, Fletcher Construction and Beca Infrastructure. Higgins role is to provide all the necessary resource and skill to deliver on the pavement construction and traffic management activities.

 
Higgins Teams Involved

Higgins Group Project Team and Higgins Contractors Auckland

 
Project Summary

The Manukau Harbour Crossing Project is an Alliance Delivery model comprising the NZ Transport Agency, Fletcher Construction, Beca Infrastructure and Higgins Contractors.

The Project will deliver safer, quicker and easier travel on SH20 across the Manukau Harbour between Mangere and Onehunga.  Part of the project involves the construction of an additional motorway bridge next to the existing bridge, providing eight lanes across the Manukau Harbour.  This Project when complete will finish the Western Ring Route Link.

 
Current Higgins Activity

Higgins are currently getting the final touches ready so that surfacing can commence on the job.  The team is focused on closing out work and finishing the job well.  Final surfacing commenced in February 2010 and will run through to April.  From April, most of the project will be surfaced.  The May to August months will see prelevelling work undertaken on the new Mangere Bridge followed by tie in work to ensure the duplicate lanes are fully utilised.

 

NZDF Ohakea Airforce - Project Takitini
NZDF Ohakea Airforce - Project Takitini

Higgins Projects Division have been awarded the Contract for Stage 2 of the NZDF Ohakea Airforce Base Project Takitini.... Read more